Loft conversion

Loft Conversions.

Non-habitable use.

 

If you wish to use your loft area for normal light storage only, boarding over the existing ceiling joists will NOT require approval under the Building Regulations. If other works are to be undertaken see the notes below.

 

Habitable Room.

 

The conversion of a roof space into a habitable room or rooms may require all or any of the following to obtain Building Regulation Consent: The general guidance set out below relate to conversions where the maximum number of storeys will not exceed three. In all other cases contact Building Control for advice.

 

The following guidelines are to advise you of certain requirements if you are considering converting your roof or loft area into a habitable room. This advice is given in general terms and will not cover all possible factors. If, after reading these notes, you are still not sure what may apply to your proposals please consult Building Control

 

  • The existing stair should be enclosed and discharge directly to an external door or be within an enclosure allowing access to two alternative exit doors front and rear of the property.
  • Installation of new floor joists
  • The replacement of existing beams or lintels
  • The exposure of the foundations
  • In the case of a house of 2 storeys or more, the upgrading of the existing upper floor ceilings to achieve a ½ hour standard offire resistance.
  • The fitting of a fixed stair or ladder with handrails and guarding.
  • The construction of a ½ hour fire resistant stair enclosure in the new storey and upgrading if necessary of the existing stair enclosure to a ½ hour standard of fire resistance which should lead to directly to the ground floor entrance door.
  • The existing doors within the stair enclosure except those to bathroom and cupboards  will need to be replaced with fire resisting doors.
  • The provision of thermal insulation within the existing roof together with a vapour barrier to reduce or eliminate condensation.
  • The provision of mains powered battery backup, interlinked smoke detection and alarm within the property. These should be installed by a registered electrician.

 

For further advice please telephone Building Control – 01279 446859 or 446827.

 

Additional Permissions that may be required.

Planning Permission and Covenant Consent may also be required to allow you to convert your garage.

You should therefore telephone Planning Development Control 01279 446577 and Covenant Control 01279 446837 for more information.