Woodleys development

We redeveloped this former garage site to construct 6 x 2-bed houses with associated parking and a new garage block to the front of the site.

The project will benefit from new hard and soft landscaping and associated parking.

The properties will support carbon emission reductions through solar panels and electric vehicle charging points

Why the work was needed

The development repurposes an underused garage site into 6 family homes to meet the needs of the Housing Needs Register and improve the overall street scene.

It offers improved parking, electric vehicle charging points and streetlighting. 

Plans

Timeline

Planning permission was granted in October 2022.

The scheme was designed by Derrick Wade Waters Ltd and Architecture & Design Services Ltd.

The contractors were TSG Building Services Plc.

Work started on site in March 2024.

The practical completion date was 24 February 2026.